Week 3 Thumb Exoskeleton

zhengh4 2015-2016 Thumb Exoskeleton

In this week, we have tested the relationship between two electromagnetic bars in order to see whether or not there will exist repulsion and attraction forces while the current was applied. After we applied the current in one electromagnetic bar, it attracted the other electromagnetic bar. However, there was no repulsion force by applying current. We positioned two electromagnetic bars …

Week 2 Thumb Exoskeleton

zhengh4 2015-2016 Thumb Exoskeleton

In this week, we have tested the force between electromagnetic bar, magnetic ring, and simple steel materials. We have discovered that the electromagnetic bar can attract magnetic ring without passing through the current but cannot repel it no matter whether there is current. We have learned that the electromagnetic bar can directly attract the magnetic ring because the ring had …

Circular UAV Week 4 and 5 Winter Quarter

zzou1 2015-2016 Circular UAV

For week 4, our team was supposed to start the manufacturing. We got all the materials for fabrication, but the CNC router did not function properly and delayed our progress. For week 5, to catch up with the timetable, our team 1) improved our fabrication models to be more efficient 2) had training and started the foam cutting process with …

Sample Testing for Next Iterative Design

EngineerMarkJ 2015-2016 Exosuit

Our final polymer samples are in and ready for testing! We are beginning to interchange our newly donated samples for our next stage prototype and see how each reacts under various loads and circumstances. With this new data we will be able to find out how the suit will react under different strains and how it affects the user’s ability …

February Status Update for Raider

roachr 2015-2016 Baja SAE Racecar Raider, 2015-2016

As we approach the midpoint of the winter quarter, it’s a perfect time to take a retrospective look at accomplishments made since our last public update. Chassis team lead Kurtis Wragg and team captain Danny Kim spearheaded the fabrication of our chassis at the end of fall quarter, and were successful in guiding the team towards delivery of a fully …