AFRL TOT week 3 update

kwilllia 2016-2017 AFRL Thermal Orientation Test Bed

This week the team worked to optimize the accuracy of the test bed. The main modifications needed were from the mechanical side of the test bed to make sure that there is not any unwanted rotation on the testbed. Our goal for accuracy is within .1 degree and to do this it needs to be completely stable wihout any movement …

Testing about to occur

kwilllia 2016-2017 AFRL Thermal Orientation Test Bed

This week, we changed the size of our rotating frame for improved stability for testing and for use by the Air force. Instead of using 1x1in bars, we used 2×2 which immensely helped the stability of the frame. we were also able to begin testing the rotation of the plate. we were able to test the rotation o f the …

Plan for rest of year

kwilllia 2016-2017 AFRL Thermal Orientation Test Bed

This week, the team took steps to planning out of the remainder of the year so that we can close out the project by june. Our steps are to finish calculations on the test equipment so that we can adjust our gear ratio properly. WE also will begin writing test procedures and test plan for the equipment to make sure …

Week 5 Setbacks

kwilllia 2016-2017 AFRL Thermal Orientation Test Bed

With the onset of midterms this week, our team worked on what we could to make progress on the project. The manufacturing team has been researching vacuum compatibility for some of our parts along with designing mounts that will help the overall safety and functionality of the machine. Unfortunately, we had a failure on the electrical side of things which …

AFRL week 5

kwilllia 2016-2017 AFRL Thermal Orientation Test Bed

This week the team continued to move closer to testing as some modifications were made to the frame of the assembly so that it would avoid interference with our motor and some of the mounts. Before testing starts, manufacturing will just have to finalize the motor mount design to put up the motor. Other than that, manufacturing will be in …

Moving Closer to Initial testing.

kwilllia 2016-2017 AFRL Thermal Orientation Test Bed

Kyle Williams- AFRL Thermal Orientation Test Bed This week our team continued to work on both the motor controls for the test bed and the modifications that need to be made to the frame. The controls team is almost finished with their motor controls, however, one of the only things holding them back is figuring out whether a limit switch …